Project Timeline

This page was last updated on January 26, 2026.  

Summer 2025 through 2027 — Anticipated construction phase

The existing Community Center will be demolished for the new combined facility to be built, while Clarke Swim Center is projected to remain open to the public throughout the construction period. Please refer to specific timeframe details below.

General Construction Notes

Typical construction hours are 7:00 AM to 5:00 PM, with weekend work authorized as necessary. Please be advised that some noise is anticipated in connection with the construction and barriers, such as fencing, will be used throughout the project for pedestrian safety.

Frequently Asked Questions      Subscribe to Project Updates

Spring 2025 — Design phase complete
Mid-June through December 2025 — Lake and pond projects
August 2025 — Existing Community Center building closes
January 2026 — Site secured and tree removal activities begin